315
BG0008001 Spirit of the Valley
Professional High School of Transport and Management Kazanlak
Prototype
P
Battery-Electric
BE
Results
Attempt 4
141.8
88.1
km/kWh
mi/kWh
Best attempt
Current Rank
22nd / 25
21 215.3 km/kWh 133.8 mi/kWh +51.8%22 141.8 km/kWh 88.1 mi/kWh
23 90.0 km/kWh 55.9 mi/kWh -36.5%Technical Inspections
Before they get on track, Prototype vehicles need to pass a series of 10 technical inspections. For some, the only goal is getting through this test. Many never even make it that far.
10/10
Complete
Complete
Passed
1. Inspection Queue Entrance
4 / 4
Passed (one driver)
2. Driver Checks
14 / 25
Passed
3. Brakes
10 / 10
Passed (one driver)
4. Driver Safety
21 / 26
Passed
5. Vehicle Dimensions
6 / 6
Passed
6. Mechanical Vehicle Design
20 / 20
Passed
7. Electrical Design
22 / 22
Passed
8. Energy Verification
10 / 10
Passed
9. Telemetry
1 / 1
Passed
10. Final Checks
4 / 4
| Event | Vehicle category | Energy class | Rank | Result |
|---|---|---|---|---|
| Europe and Africa 2025 | Prototype P | Battery Electric Battery Electric | - | Did not pass technical inspection |